Installation of panel mouldings

midres-ceiling-roses-installation by NMC Copley Decor

All of our WALLSTYL® panel mouldings are made from lightweight extruded polystyrene (HDPS) with a matt white acrylic primer.   They are waterproof and intended for indoor use. 

1 Preperation
noel marquet 2 chair rails installation manual EN A4 2022 09 - Nöel & Marquet
  • All mouldings should be fixed to clean plaster, before starting remove any old wallpaper, paint, grease or dirt.  If applying to new plaster make sure it has been sealed/primed first.
  • Determine the height of the panel moulding on the wall and mark the
    position on the wall using a chalk line or a laser level.

3 Prepare the edges

Capture - Nöel & Marquet
  • Lightly sand the cut edges and the edges of the moulding
    with fine sandpaper (150 grit or less) or cutter and remove the
    sawdust with a damp sponge

2 Cutting the panel moulding 

Image 9 - Nöel & Marquet
  • Cut the panel mouldings to size in the mitre box using a fine tooth saw.
  • When using an electric mitre saw to cut WALLSTYL® panel moiulding, the blade must be suitable for synthetic materials.

4 Gluing the surface 

Image 5 - Nöel & Marquet
  • Using a cartridge gun, generously apply the ADEFIX® adhesive in
    a continuous bead on gluing surfaces

5 Installation

Image 6 - Nöel & Marquet
  • Position the chair rails against the wall; strengthen their attachment
    if necessary with steel nails or dots of hot glue.
  • WALLSTYL® and ARSTYL® mouldings with a height / span smaller
    than 8 cm and NOMASTYL® profiles:
    apply ADEFIX® adhesive to the cuts and corner mitres so that it
    forms a 3 mm joint.
  • WALLSTYL® and ARSTYL® mouldings with a height / span more
    than 8 cm: apply ADEFIX® PLUS adhesive to the cuts and corner
    mitres so that it forms a 3 mm joint.

6 Finishing

Image 8 - Nöel & Marquet
  • Leave the glue to dry (min. 6h) then finish the joints with
    ADEFIX® adhesive.
  • Finish the wall joints as well as the mitre joints with ADEFIX®
    adhesive.
  • Leave to dry (min. 6h). Apply the paint finish during the next 4
    weeks